Order Process

SIPCO aim for an 10 weeks typical lead-time from order to site delivery - see below. This is based on 100% information availability from the client and architect:


WEEK 1
- Receive and accept SIPCO estimate
WEEK 2
- SIPCO invoice for 10% to cover design fees
-
Commission engineers report
WEEK 4
- Receive engineers design, review estimate and issue fixed price, Any savings passed back to client
WEEK 5
- Commence SIP design
WEEK 7
- Receive signed approval drawings
-
Forward SIP design to client/architect for signature
WEEK 8
- Start manufacturing process
WEEK 10
- Delivery